Description
Location: Grantsville, UT
Project Duration: 3 months
Project Type: Existing Substation Expansion
Scope of Work: Expand the substation to accommodate a new bay position for a renewable energy solar tie line
Unique Problem:
Anytime a new pad is installed, it is crucial that it provides a solid foundation that will sufficiently support the weight of the load it will hold. Installing a new pad at this substation was a challenge because the existing structure was built on soft, muddy, swamp-like clays and soils at the edge of the Great Salt Lake. Our experienced personnel worked with a team of engineers to develop a special installation process to ensure the pad would be solid, eliminating the risk of soft spots, sinking foundations, or leaning towers.
TAKE THE NEXT STEP
Put Grade Tech Services to work on your next project. Contact us for more information or to request a bid.













